Location: Anova Group – Long an Province.
After the time for design and tender, on the date 21, April , 2012, at the Construction Site, the Owner ( Anova Corp and SAIGON VET), Contractor ( Gia Thuy) and Consultants ( VEV) had made the Ground breaking ceremony to start the Construction Work. The 3,000 sqm building for Complexity of Medical Store, Cooling and Cold Store would been completed within 4.5 months. This building had been designed a high standard of GSP ( Good Storage Practice) of WHO.
Mr Nguyen Truong Hai ( GD of VEV) and the Head of Supervisor of VEV pray and incense for a luck work.
Mr Hieu ( Representative of Anova group ) and the Project Manager of Gia Thuy pray and incense for a luck work.
The Piling Work start right after the Ground Breaking Ceremony.